Gists

Lagos-Ibadan Expressway to be completed 2022 – Fashola

The Minister of Works and Housing, Babatunde Fashola, has said the Lagos-Ibadan Expressway will be completed in the first quarter of 2022.

He said this during an interview on Bond FM on Sunday.

According to him, the delay in the completion of the project was caused by the government’s inability to shut it down totally.

He noted that the 80 kilometres of the 127-kilometre road had been completed, urging road users to be patient with the government.

The minister said, “As we speak, 80km has been completed. Some of the parts of the road used today have been completed.

“We cannot shut the road totally. The number of vehicles passing the road is not less than 40,000. We can’t shut Lagos-Ibadan road like that. The road should be completed in 2022. The construction will end in 2022.

PROMOTE YOUR | MUSIC| VIDEO | COMEDY SKIT | MIXTAPES  HERE ON CONNECTNAIJA CALL/WHATSAPP : +2348122390211

Related posts

Leave a Comment

Start Chat
1
Chat With DJ Gambit
Hello!😎
How Can I help You?
%d bloggers like this: